LP turbine inner cylinder for Fangjiashan Unit 1 conventional island in place

Friday, 20 July 2012 16:38

Key words: LP turbine inner cylinder, Fangjiashan Unit 1, in place

On July 18, the low-pressure (LP) steam turbine inner cylinder for Fangjiashan Unit 1 conventional island was put in place.

The LP inner cylinder including one major structure and two exhaust areas are used to restrict steam flow and support the diaphragms.