First NPP unit in Fujian expected to be commissioned this year

Monday, 18 June 2012 16:20

Key words: NPP unit, Fujian, commissioned

On June 15, officials of Ningde NPP announced that its Unit 1 was expected to be put into operation at the end of the year.

So far the NPP construction has been going smoothly. Unit 1 and 2 has been completed by 89.5%, and Unit 3 and 4 by 50.3%.

The project involves six 1000MW units, four of which belong to Phase one which costs RMB 52 billion. The four are planned to be commissioned between 2012 and 2015, one for each year.

Source: http://www.china-nea.cn

 